Method for data center storage evaluation framework simulation
Abstract
A method for simulating a data center is provided and a non-transitory computer-readable storage medium having recorded thereon a computer program for executing the method of simulating a data center. The method includes generating, by a first application, a simulation program of a data center using a hardware configuration file and a functional description file; and executing, by a simulator, a simulation on the simulation program by obtaining, by the simulator, at least one record from a second application and producing at least one job corresponding to the at least one record, entering the at least one job in a job queue, and executing a flow, by a third application, using a job selected from the job queue.
Claims
exact text as granted — not AI-modifiedWhat is claimed is:
1 . A method of simulating a data center, the method comprising:
generating, by a first application, a simulation program of a data center using a hardware configuration file and a functional description file; and executing, by a simulator, a simulation on the simulation program by:
obtaining, by the simulator, at least one record from a second application and producing at least one job corresponding to the at least one record,
entering the at least one job in a job queue, and
executing a flow, by a third application, using a job selected from the job queue.
2 . The method of claim 1 , further comprising generating, by the first application, models of devices associated with the data center.
3 . The method of claim 2 , wherein the devices associated with the data center include at least one of a central processing unit (CPU), memory including a dual in-line memory application (DIMM)/nonvolatile DIMM (NVDIMM)), a hard disk drive (HDD), a solid state drive (SSD), a network interface controller (NIC), a network switch, an operating system, a workload application, a file system, a driver, a device with flows and blocks, and interfaces including an address/data (ADDR/DATA) bus, a peripheral component interconnect (PCI) bus, a PCI express (PCI-e) bus, serial advanced technology attachment (SATA) bus, and an intelligent drive electronics (IDE) bus.
4 . The method of claim 1 , further comprising outputting, by the simulator, a performance metric associated with a single device or the data center.
5 . The method of claim 4 , wherein the performance metric includes at least one of input/output (I/O) performance, energy consumption, total cost of ownership (TCO), reliability, and availability associated with the single device or the data center.
6 . The method of claim 5 , wherein I/O performance includes throughput, bandwidth, and total execution time.
7 . The method of claim 4 , further comprising performing load balancing and topology reorganization to improve performance of the data center based on the performance metric.
8 . The method of claim 1 , further comprising storing the at least one record in a file application in the simulator.
9 . The method of claim 8 , further comprising:
decoding the job to obtain a flow identifier (ID) and metadata by the third application; initializing and operating the data center by the third application; and looking up corresponding device object descriptions by the third application.
10 . The method of claim 1 , wherein the data center includes at least one multiple host machine, wherein a host machine is one of a virtual machine (VM) and a hypervisor.
11 . The method of claim 1 , wherein the first application includes a data center storage evaluation framework (DCEF) application.
12 . The method of claim 1 , wherein the third application includes a job distribution application.
13 . The method of claim 1 , wherein the second application includes a trace file application.
14 . A non-transitory computer-readable recording medium having recorded thereon a computer program for executing a method of simulating a data center, the method comprising:
generating, by a first application, a simulation program of a data center using a hardware configuration file and a functional description file; and executing, by a simulator, a simulation on the simulation program by: obtaining, by the simulator, at least one record from a second application and producing at least one job corresponding to the at least one record; entering the at least one job in a job queue; and executing a flow, by a third application, using a job selected from the job queue.
15 . The non-transitory computer-readable recording medium of claim 14 , the computer program further comprising generating, by the first application, models of devices associated with the data center.
16 . The non-transitory computer-readable recording medium of claim 15 , wherein the devices associated with the data center include at least one of a central processing unit (CPU), memory including a dual in-line memory application (DIM)/nonvolatile DIMM (NVDIMM)), a hard disk drive (HDD), a solid state drive (SSD), a network interface controller (NIC), a network switch, an operating system, a workload application, a file system, a driver, a device with flows and blocks, and interfaces including an address/data (ADDR/DATA) bus, a peripheral component interconnect (PCI) bus, a PCI express (PCI-e) bus, serial advanced technology attachment (SATA) bus, and an intelligent drive electronics (IDE) bus.
17 . The non-transitory computer-readable recording medium of claim 14 , the computer program further comprising outputting, by the simulator, a performance metric associated with a single device or the data center.
18 . The non-transitory computer-readable recording medium of claim 17 , wherein the performance metric includes at least one of input/output (I/O) performance, energy consumption, total cost of ownership (TCO), reliability, and availability associated with the single device or the data center.
19 . The non-transitory computer-readable recording medium of claim 18 , wherein I/O performance includes throughput, bandwidth, and total execution time.
20 . The non-transitory computer-readable recording medium of claim 17 , further comprising performing load balancing and topology reorganization to improve performance of the data center based on the performance metric.Join the waitlist — get patent alerts