Method for increasing production rate of horizontal wells having hydraulic fractures formed along a horizontal segment of the well by drilling drain holes to intersect the hydraulic fractures is provided.
Claims
exact text as granted — not AI-modified1 . A method for producing fluid from a subsurface reservoir, comprising:
drilling and completing a horizontal well having a horizontal segment in the subsurface reservoir and a casing; creating a plurality of hydraulic fractures spaced apart along the horizontal segment of the well; cutting a window at a selected location in the casing of the well and drilling a drain hole having a main body from the window, the main body of the drain hole being spaced apart from the horizontal segment of the well and drilled so as to intersect a hydraulic fracture extending from the horizontal segment; and producing fluid from the well.
2 . The method of claim 1 wherein fluid is produced from the well at a production rate for a selected time before cutting a window in the casing of the well and drilling a drain hole.
3 . The method of claim 1 wherein a plurality of drain holes having main bodies spaced apart from the horizontal segment of the well are drilled at spaced apart angles with respect to the horizontal well in a plane perpendicular to the axis of the horizontal well.
4 . The method of claim 2 wherein the selected time is after the time required for the production rate of the well to decrease from an initial production rate of the well to less than one-half (½) the initial production rate.
5 . The method of claim 1 wherein the drain hole is further drilled so as to intersect a zone of natural fractures in the subsurface reservoir or selected zones in the reservoir.
6 . The method of claim 1 wherein the selected location to drill a drain hole is in a vertical segment of the horizontal well.
7 . The method of claim 1 wherein the drain hole is drilled with a drilling motor and bent sub assembly.
8 . The method of claim 1 wherein the drain hole is drilled with a jet drilling assembly.
9 . The method of claim 1 wherein the main body of the drain hole is drilled at a selected distance from the horizontal segment of the well, the selected distance being greater than the estimated radius of a damage zone around the horizontal segment.
10 . The method of claim 1 wherein the drain hole is drilled to be undulating or sinusoidal.
11 . The method of claim 1 wherein the drain hole is branched before intersecting a hydraulic fracture such that two or more branches of the drain hole intersect a hydraulic fracture.
12 . The method of claim 1 wherein at least a segment of the main body of the drain hole is drilled with fluid pressure in the drain hole less than fluid pressure in the subsurface reservoir.
13 . The method of claim 1 further comprising placing a slotted liner, a pierced plastic pipe, a sand screen, resin-coated sand or a casing in the drain hole.
14 . The method of claim 1 further comprising injecting fluid at hydraulic fracturing conditions from a drain hole by placing straddle packers on a work string and pumping fluid from the work string between the straddle packers.
15 . The method of claim 14 wherein the straddle packers are placed across an existing hydraulic fracture.
16 . The method of claim 14 wherein the straddle packers are placed between existing hydraulic fractures.
17 . A method for producing fluid from a subsurface reservoir, comprising:
drilling and completing a first horizontal well having a horizontal segment in the subsurface reservoir; creating a plurality of hydraulic fractures spaced apart along the horizontal segment of the first horizontal well; drilling a second horizontal well having a horizontal segment drilled so as to intersect a hydraulic fracture extending from the horizontal segment of the first horizontal well; and producing fluid from the at least one of the wells.
18 . The method of claim 17 wherein the second horizontal well is drilled so as to intersect a hydraulic fracture nearer to the heel of the horizontal segment of the first well.
19 . The method of claim 17 wherein the second horizontal well is drilled so as to intersect a hydraulic fracture nearer to the toe of the horizontal segment of the first well.
20 . A method for producing fluid from a subsurface reservoir, comprising:
drilling and completing a horizontal well having a horizontal segment in the subsurface reservoir and a casing; cutting a window in the casing of the well and drilling a drain hole having a main body from a selected location in the well, the main body of the drain hole being directed so as to intersect a natural fracture zone in the reservoir; and producing fluid in the well.
21 . A method for producing fluid from a subsurface reservoir, comprising:
drilling a horizontal well having a horizontal segment in the subsurface reservoir, the horizontal segment being an open hole; creating a plurality of hydraulic fractures spaced apart along the horizontal segment of the well; drilling a drain hole having a main body at a selected location along the horizontal segment, the main body of the drain hole being spaced apart from the horizontal segment of the well and drilled so as to intersect a hydraulic fracture extending from the horizontal segment; and producing fluid from the well.Join the waitlist — get patent alerts