A method is provided for constructing railways for a rubber-wheeled AGT system, including: constructing guideways on vertical walls of a light rail vehicle road bed, arranging steel bars at a place where railways will be formed, installing molds around the arranged steel bars; pouring concrete in the molds; and forming, using a pressing unit of a finisher, the railways applied with concrete such that the railways have a same trace as the guideways by moving a finisher along the guideways forming a top surface of the concrete, and curing the concrete.

Claims

exact text as granted — not AI-modified
1 . A method for constructing railways for a rubber-wheeled AGT system, comprising:
 constructing guideways on vertical walls of a light rail vehicle road bed;   arranging steel bars at a place where railways will be formed;   installing molds around the arranged steel bars;   pouring concrete in the molds; and   forming, using a pressing unit of a finisher, the railways applied with concrete such that the railways have a same trace as the guideways by moving a finisher along the guideways forming a top surface of the concrete; and curing the concrete.   
     
     
         2 . The method of  claim 1 , further comprising, after arranging the steel bars, installing drain pipes and system pipes. 
     
     
         3 . The method of  claim 1 , further comprising, after curing the concrete, line grooves for improving frictional force of the concrete. 
     
     
         4 . The method of  claim 1 , further comprising, after arranging the steel bars, pressing the arranged steel bars using the finisher running along the guideways such that the arranged steel bars have a same trace as the guideways. 
     
     
         5 . The method of  claim 2 , further comprising, after arranging the steel bars, pressing the arranged steel bars using the finisher running along the guideways such that the arranged steel bars have a same trace as the guideways. 
     
     
         6 . The method of  claim 3 , further comprising, after arranging the steel bars, pressing the arranged steel bars using the finisher running along the guideways such that the arranged steel bars have a same trace as the guideways. 
     
     
         7 . The method of  claim 4 , further comprising, after arranging the steel bars, pressing the arranged steel bars using the finisher running along the guideways such that the arranged steel bars have a same trace as the guideways.

Join the waitlist — get patent alerts