US2012317918A1PendingUtilityA1
Connection of metal segments of a tower
Est. expiryJun 14, 2031(~4.9 yrs left)· nominal 20-yr term from priority
Y10T29/49623Y02E10/728E04H 12/085E04H 12/08
25
PatentIndex Score
0
Cited by
0
References
0
Claims
Abstract
A method for connecting metal segments of a tower includes connecting at least two metal segments of the tower by the use of connecting elements. A paste is provided between the tower segments for filling at least a part of a gap between the segments. The paste is cured, wherein the cured paste absorbs at least a part of a load originated by the connected segments.
Claims
exact text as granted — not AI-modified1 . A method for connecting metal segments of a tower, comprising the steps of:
connecting at least two metal segments of the tower via a connecting element, providing a paste between the tower segments for filling at least a part of a gap between the metal segments, and curing the paste, wherein the cured paste absorbs at least a part of a load originated by the connected segment.
2 . The method according to claim 1 , wherein the step of curing the paste is performed by applying heat.
3 . The method according to claim 1 , wherein at least a part of the provided paste, applied to the gap, and is protected against ambient influence for at least a part of the curing period.
4 . The method according to claim 1 , wherein metal segments of a wind turbine tower are connected.
5 . An arrangement for the connection of at least two tower segments of a metallic tower:
a connecting device for connecting the at least two segments, wherein at least a part of a gap between the segments is filled by a paste which is arranged between the tower segments, and wherein the paste is cured, so as to absorb at least a part of a load originated by the connected segments.
6 . The arrangement according to claim 5 , wherein the paste is prepared to cure at an ambient temperature between −20° C. and +30° C.
7 . The arrangement according to claim 5 , wherein the paste is prepared to cure at a temperature above +30° C.
8 . The arrangement according to claim 5 , wherein the paste is prepared to cure under the influence of ambient or atmospheric weather conditions like rain, snow or sunshine.
9 . The arrangement according to claim 5 , wherein the paste is prepared for an operating temperature range between −40° C. and +60° C.
10 . The arrangement according to claim 5 , wherein the paste shows a predetermined high flexural resistance and/or a predetermined low creep characteristic.
11 . The arrangement according to claim 5 , wherein the paste is thixotropic before it is cured.
12 . The arrangement according to claim 5 , wherein the paste comprises a polymer or a non-shrink grout.
13 . The arrangement according to claim 12 , wherein the polymer is a polyurethane-hybrid or an epoxy resin or a polymer-bitumen.
14 . A wind turbine tower comprising:
a plurality of metallic tower segments, and an arrangement according to claim 5 for connecting at least two of the tower segments.Join the waitlist — get patent alerts
Track US2012317918A1 — get alerts on status changes and closely related new filings.