US2012198787A1PendingUtilityA1

Pre-pave Waterproof Construction Method

Assignee: MO YU-CHENGPriority: Feb 8, 2011Filed: Feb 8, 2011Published: Aug 9, 2012
Est. expiryFeb 8, 2031(~4.5 yrs left)· nominal 20-yr term from priority
E04B 1/66
22
PatentIndex Score
0
Cited by
0
References
0
Claims

Abstract

A pre-applied waterproof construction method contains steps of: A. paving a plurality of lining fabric materials and connecting the lining fabric materials on a number of predetermined base structures; B. spraying waterproof coating materials on a surface of each lining fabric material to form a seamless waterproof coating material; C. applying a layer of adhesion promoter on a surface of the waterproof coating after spraying the waterproof coating to reinforce an adhesion of a concrete connecting with the waterproof coating materials, such that a gap is not formed between the concrete and the waterproof coating materials to obtain a waterproof effect.

Claims

exact text as granted — not AI-modified
1 . A pre-applied waterproof construction method comprising steps of:
 A. Paving a plurality of lining fabric materials and connecting the lining fabric materials on a number of predetermined base structures;   B. Spraying waterproof coating materials on a surface of each lining fabric material to form a seamless waterproof coating material;   C. Applying a layer of adhesion promoter on a surface of the waterproof coating after spraying the waterproof coating to reinforce an adhesion of a concrete connecting with the waterproof coating materials.   
     
     
         2 . The pre-applied waterproof construction method as claimed in  claim 1 , wherein the waterproof coating materials are selected from polyurea resins, polyurethane resins, rubberized asphalts and mixed resins made of polyurea resin, polyurethane resins, rubberized asphalts. 
     
     
         3 . The pre-applied waterproof construction method as claimed in  claim 1 , wherein the waterproof coating materials at a certain quantity are heated and pressured by a spraying device. 
     
     
         4 . The pre-applied waterproof construction method as claimed in  claim 2 , wherein the waterproof coating materials at a certain quantity are heated and pressured by a spraying device. 
     
     
         5 . The pre-applied waterproof construction method as claimed in  claim 1 , wherein the lining fabric materials are selected from polyester fabrics, non-woven fabrics and canvas. 
     
     
         6 . The pre-applied waterproof construction method as claimed in  claim 1 , wherein the base structures are selected from soil layers, retaining piles, and slurry walls. 
     
     
         7 . A pre-applied waterproof construction method comprising steps of:
 A. Spraying waterproof coating materials on a surface of each support material;   B. Paving a plurality of support materials with the waterproof coating materials and on a number of base structures;   C. Applying the waterproof coating materials onto the joints between the lining fabric materials to generate a seamless state;   D. Applying a layer of adhesion promoter on a surface of the waterproof coating materials to reinforce an adhesion of a concrete connecting with the waterproof coating materials.   
     
     
         8 . The pre-applied waterproof construction method as claimed in  claim 7 , wherein the waterproof coating materials are selected from polyurea resins, polyurethane resins, rubberized asphalts and mixed resins made of polyurea resin, polyurethane resins, rubberized asphalts. 
     
     
         9 . The pre-applied waterproof construction method as claimed in  claim 7 , wherein the waterproof coating materials at a certain quantity are heated and pressured by a spraying device. 
     
     
         10 . The pre-applied waterproof construction method as claimed in  claim 8 , wherein the waterproof coating materials at a certain quantity are heated and pressured by a spraying device. 
     
     
         11 . The pre-applied waterproof construction method as claimed in  claim 7 , wherein the lining fabric materials are selected from polyester fabrics, non-woven fabrics and canvas. 
     
     
         12 . The pre-applied waterproof construction method as claimed in  claim 7 , wherein the base structures are selected from soil layers, retaining piles, and slurry walls.