US2011268565A1PendingUtilityA1
Tunnel turbine system generates potential energy from dorment kinetic energy
Est. expiryApr 13, 2030(~3.7 yrs left)· nominal 20-yr term from priority
Inventors:Mujeeb Ur Rehman Alvi
Y02E10/20F03B 3/18F05B 2220/20F03B 3/186F05B 2260/601Y02B10/50Y02E10/72F05B 2220/60Y02E10/728F03B 17/062F03D 9/00F05B 2210/40F03D 9/25Y02E10/74F03D 9/32
29
PatentIndex Score
0
Cited by
0
References
0
Claims
Abstract
A generator system includes a pipe line which includes a control valve for diverting input gas or liquid into a pair of bypass pipe lines, whose output is coupled with two nozzle venture inlets in a turbine housing. Gas or liquid entering the turbine housing through the nozzle venture inlets rotates a turbine impellor having a generator shaft to generate energy. Gas or liquid exiting from the turbine housing, along with diverted input gas or liquid, pass through an ejector device which eliminates back pressure and restores any pressure loss.
Claims
exact text as granted — not AI-modified1 : “Tunnel Turbine System” Generates Potential Energy from Kinetic Energy in Dorment state present in a Pipe Line Network system; wherein Stock (Gas or Liquid) under Velocity Pressure is in transit; makes enormous Potential Energy available without incurring any Fuel Usage or Greenhouse Gas Emission or Environment Pollution.
2 : “Tunnel Turbine”; as claimed in claim 1 ; wherein stock (Gas or Liquid) in transit under Velocity Pressure subsists as a vehicle in a Pipe Line Network System; has inbuilt Kinetic Energy in Dormant state—contained therein by inherent Static Pressure.
3 : “Tunnel Turbine”; as claimed in claims 1 and 2 , wherein Composite Unit Assembly has two Devices—integrated in Pipe Line Network System; each Device has a different function, purpose and object to accomplish, viz; “Generator Device”—I is coupled with “Ejector Contraption Device”—II in “Tunnel Turbine System”; FIG. 1 —jointly/individually efficiently utilizes and supplements the Dorment Kinetic Energy potential inherently present in the Pipe Line Network System 14 .
4 : “Tunnel Turbine”; as claimed in claims 2 and 3 ; wherein the power to drive is Kinetic Energy in Dorment State inherently present as Velocity Pressure in Pipe Line Network System 14 ; wherein “Generator Device”—I activates Kinetic Energy from Dormant State into Potential Energy, and; “Ejector Contraption Device”—II supplements “Generator Device”—I and restores Velocity Pressure loss if any in Pipe Line System 14 .
5 : “Tunnel Turbine”; as claimed in claims 2 , 3 and 4 ; wherein stock 1 in transit under Velocity Pressure through Tunnel 12 is diverged to pass through two Control Valves 2 and 3 ; Control Valve 2 controls major outflow of stock 1 from Tunnel 12 into TWO Conduit Bypass Pipe Lines 2 a —connects Two Nozzle Venturi Inlets 6 in “Generator Device”—I, and; Control Valve 3 controls balance outflow of stock 1 from Tunnel 12 into One Conduit Bypass Pipe Line 3 a —connects Inlet 9 in “Ejector Contraption Device”—II.
6 : “Generator Device”—I of Tunnel Turbine System as claimed in claims 3 , 4 and 5 ; Generates Potential Energy from Kinetic Energy in Dorment state; comprises of; Pipe Line System 4 ; Stock 1 in transit under high Velocity Pressure; Control Valve 2 controls major outflow of Stock 1 into two Conduit Bypass Pipe Lines 2 a ; Nozzle Venturi Inlets 6 ; Turbine Housing 4 ; Turbine Impellor 5 ; Generator Shaft 8 ; two Outlets 7 .
7 : “Generator Device”—I: of Tunnel Turbine System; as claimed in claims 5 , & 6 ; more particularly; major outflow of stock through two Nozzle Venturi Inlets 6 strikes Turbine Impellor 5 in Turbine Housing 4 from two different angles/directions with great Velocity Pressure activates (turns) the Generator Shaft 8 at high speed.
8 : “Generator Device”—I: of Tunnel Turbine System; as claimed in claims 6 & 7 ; the stock 1 thereafter Exits from the Turbine Housing 4 through two Outlets 7 without being contaminated continues journey to be used as Fuel, Feedstock or Stored at destination; least effecting Pipe Line Network System 14 haulage efficiency.
9 : “Generator Device”—I: of Tunnel Turbine System; as claimed in claims 6 , 7 , & 8 ; the number of Pipe Conduit Bypass Lines 2 a and Nozzles Inlets 6 thereof be increased as and when required to strike the Turbine Impellor 5 in Turbine Housing 4 from two or more different angles/directions to impede any energy loss and enhance Generation efficiency, according also increases the number of Outlets 7 .
10 : “Tunnel Turbine System”; as claimed in preceding claims, more particularly the inbuilt Kinetic Energy in Dorment state in Tunnel 12 ; wherein the “Generator Device—I” integrated in Pipe Line Network System 14 generates Potential Kilowatt Hours (KWh) without Fuel Usage—does Not dissipate any Greenhouse Gas (Carbon) Emission in environment.
11 : “Ejector Contraption Device”—II: of Tunnel Turbine System; as claimed in claims 1 , 3 , 4 , & 5 comprises of; Pipe Line 14 ; stock (Gas or Liquid) 1 ; Control Valve 3 ; One Conduit Bypass Pipe Line 3 a ; stock 1 Inlet 9 ; Ejector Contraption Body 10 incorporated and built around the Tunnel Body 13 ; Slit Venturi Outlet 11 —Slit incision is built-in Tunnel Body 13 circumference concealed inside Contraption Body 10 and opens into Tunnel passage 12 .
12 : “Ejector Contraption Device”—II: of Tunnel Turbine System; as claimed in claim 11 ; more particularly; the high Velocity Pressure outflow of stock 1 through Conduit Bypass Pipe Line 3 a connects Inlet 9 in Ejector Contraption Body 10 .
13 : “Ejector Contraption Device”—II: of Tunnel Turbine System; as claimed in claims 11 , & 12 ; more particularly; the stock 1 under high Velocity Pressure is Self Ejected into Tunnel passage 12 through Slit Venturi Outlet 11 concealed inside Ejector Contraption Body 10 wherein it causes Vortex 15 in Tunnel passage 12 just above the Slit Venturi Outlet 11 and creates Vacuum 16 just below the Slit Venturi Outlet 11 .
14 : “Ejector Contraption Device”—II: of Tunnel Turbine System; as claimed in claims 11 , 12 & 13 ; wherein Vacuum 16 formation just below the Slit Venturi Outlet 11 in Tunnel passage 12 extracts with greater impetus stock 1 Exiting from Outlet 7 of “Generator Device I”—eliminates Back Pressure Buildup if any in “Generator Device”—I.
15 : “Tunnel Turbine System”; as claimed in preceding claims, more particularly balance stock 1 under high Velocity Pressure—diverged to pass through Control Valve 3 and Bypass Pipe Line 3 a into Inlet 9 of Ejector Contraption Body 10 is self ejected through concealed Slit Venturi Outlet 11 , wherein Vortex 15 formation above Slit Venturi Outlet 11 accelerates incoming stock flow from “Generator Device I” with Volume increase from Low Velocity to High Velocity—restores Velocity Pressure loss if any to stock 1 in transit on onward haulage in the Pipe Line Network System 14 .
16 : “Tunnel Turbine System”; as claimed in preceding claims, wherein inbuilt friendly Kinetic Energy in Dorment state—inherently present in Pipe Line Network System—is efficiently harvested by Composite Unit Assembly of two Devices, viz; “Generator Device—I” and; “Ejector Contraption Device—II”; without effecting haulage efficiency of stock 1 in transit under Velocity Pressure in Pipe Line Network System 14 , or exposing contents in transit therein to contamination.
17 : “Tunnel Turbine System”; as claimed in preceding claims, wherein each Device has a different function, purpose and objective to achieve, but are conducive/productive to each other to achieve efficient Potential Energy generation and Velocity Pressure loss restoration in the Pipe Line Network System 14 .
18 : “Tunnel Turbine System”; “Generator Device”—I: and “Ejector Contraption Device”—II: hereinbefore referred to in any one of the proceeding claims, is designed, constructed, arranged and adopted to operate substantially as hereinbefore described with reference to and shown respectively in FIG. 1 of the accompanying drawing.Join the waitlist — get patent alerts
Track US2011268565A1 — get alerts on status changes and closely related new filings.